Optimasi Pembangunan Tangki Air Tanah dan Sanitasi Menggunakan Metode Program Evaluation and Review Technique (PERT) dan Critical Path Metode (CPM) Agar Efektif Biaya Dan Waktu
DOI:
https://doi.org/10.47065/arbitrase.v3i3.684Keywords:
Ground Water Tank; PERT; CPM; Project TimeAbstract
The success or failure of project implementation is often due to the lack of planning of project activities and ineffective control, so that project activities are inefficient, this will result in delays, decreased quality of work, and increased implementation costs. Project management is carried out to manage the project from start to finish. This study aims to determine the optimal time and cost of a ground water tank and sanitation development project at Al-Mulk Hospital, Sukabumi City. The more optimal the time obtained will help the company complete the project at optimal cost. The method used here uses quantitative and data collection techniques through observation, interviews and literature. With the method of data analysis using the Program Evaluation and Review Technique (PERT) and Critical Patch Methode (CPM).
Downloads
References
Arif Rakhmat Ekanugraha. (2016). EVALUASI PELAKSANAAN PROYEK DENGAN METODE CPM dan PERT (Studi Kasus Pembangunan Terminal Binuang Baru Kec. Binuang).
Dannyanti, E. 2010. Optimalisasi Pelaksanaan Proyek dengan Metode Pert dan CPM (Studi Kasus Twin Tower Building Pascasarjana Undip). Skripsi, FT Undip. Semarang.
E Wardani, N. M., Musdalifah, S., Lusiyanti, dan D., & Studi Matematika Jurusan Matematika, P. (2018). METODE PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)-CRITICAL PATH METHOD (CPM). In Jurnal Ilmiah Matematika dan Terapan (Vol. 15).
Gray, C., Simanjuntak, P., Lien K.S., Mspaitella, P.F.L., Varley,R.C.G. 2007. Pengantar Evaluasi Proyek. Gramedia Pustaka Utama. Jakarta.
Kerzner, H. (2003). Manajemen Proyek: Pendekatan Sistem untuk Perencanaan, Penjadwalan, dan Pengendalian (edisi ke-8). New Jersey : John Wiley & Son Inc.
Muhamad, Amiruddin HI. 2013. Optimalisasi Pelaksanaan Proyek dengan Metode PERT dan CPM (Studi Kasus di Gedung SMA Negeri 1 Tidore Kepulauan, Provinsi Maluku Utara). Skripsi. Fakultas Teknik, UMY. Yogyakarta
Maddeppungeng A, Rindu Twidi B, Fisi Rayigianti. (2013). Analisis Waktu dan Biaya Menggunakan Metode Earned Value dan Optimasi Menggunakan Metode CPM. Jurnal Fondasi, Volume 3 Nomor 1.
Oka, J., Kartikasari, D., Bisnis, P. A., Politeknik, T., & Batam, N. (2017). EVALUASI MANAJEMEN WAKTU PROYEK MENGGUNAKAN METODE PERT DAN CPM PADA PENGERJAAN “PROYEK REPARASI CRANE LAMPSON” DI PT MCDERMOTT INDONESIA. In Jurnal Administrasi Bisnis (Vol. 1, Edisi 1).
Pembimbing, D., & Sudaryanto, D. B. (n.d.). OPTIMALISASI PELAKSANAAN PROYEK DENGAN METODE PERT DAN CPM (Studi Kasus Twin Tower Building Pasca Sarjana Undip) EKA DANNYANTI.
Institut Manajemen Proyek. (2008). A Guide To The Project ManagementBody of Knowledge (edisi ke-4).
Ridho, M. Rizki & Syahrizal. 2014. Evaluasi Penjadwalan Waktu dan Biaya Proyek dengan Metode PERT dan CPM (Studi Kasus: Proyek Pembangunan Gedung Kantor Badan Pusat Statistik Kota Medan di Jl. Gaperta Medan, Sumatera Utara). Jurnal Teknik Sipil USU, Vol. 3, No. 1.
Sahid, Dadang S.S. 2012. Implementasi Critical Path Method dan PERT Analysis pada Proyek Global Technology for Local Community. Jurnal Teknologi Informasi dan Telematika, Vol. 5: 14-22.
Siregar, A. C., & Iffiginia, I. (2019). Penggunaan critical path method (CPM) untuk evaluasi waktu dan biaya pelaksanaan proyek. Teknika: Jurnal Sains Dan Teknologi, 15(2), 102. https://doi.org/10.36055/tjst.v15i2.6816
Sofyan Tsauri, Muhammad. (2013). Analisis Penjadwalan Proyek dan Optimasi Percepatan Durasi Proyek dengan Menggabungkan Metode PERT dan CPM : Studi Kasus Proyek Pembangunan Gedung Universitas Pendidikan (UPI) Kampus Serang. Jurnal Fondasi Volume 3 nomor 1 Jurnal Untirta, 46-60.
Susilo, Yayuk Sundari. 2012. Analisis Pelaksanaan Proyek dengan Metode CPM dan PERT (Studi Kasus pada Proyek Pelaksanaan Main Stadium University of Riau). Jurnal Fakultas Teknik Sipil Universitas Riau: 1-16.
Taurusyanti, D., & Lesmana, M.F. (2015).Optimalisasi Penjadwalan Proyek Jembatan Girder Guna Mencapai Efektifitas Penyelesaian dengan Metode Pert dan Cpm pada PT Buana Masa Metalindo. JIMFE (Jurnal Ilmiah Manajemen Fakultas Ekonomi), Volume 1 No. 1, 32-36
Bila bermanfaat silahkan share artikel ini
Berikan Komentar Anda terhadap artikel Optimasi Pembangunan Tangki Air Tanah dan Sanitasi Menggunakan Metode Program Evaluation and Review Technique (PERT) dan Critical Path Metode (CPM) Agar Efektif Biaya Dan Waktu
ARTICLE HISTORY
How to Cite
Issue
Section
Copyright (c) 2023 Muhammad Anfaal Al Ghifari, Gustian Djuanda

This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under Creative Commons Attribution 4.0 International License that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (Refer to The Effect of Open Access).